Charlie Demerjian says that NVIDIA is currently promising its partners to have the GT300 to them by mid-October. Charlie goes on to explain how that goal might be tough to hit considering all the work that has to be done between now and then.
If it tapes out like we heard in June, lets just say June 1, that is a mighty tight timeline. Assuming four-week months for brevity, if you hot lot the test batches, you will get first silicon back in eight weeks. That puts testing of A0 silicon starting August 1, and that will take about two weeks. If there are no bugs, or very minor ones, production can start on August 15, and that takes 10-12 weeks. Ten weeks from wafers in brings you to Nov 1, which is slightly after the claimed Oct 15 date.